Prettyman Courthouse, Chiller Commissioning

Henry Adams provided the fundamental commissioning for the E. Barrett Prettyman Courthouse. Commissioning was performed for the replacement of three 5kV chiller starter. The project included development of the commissioning plan, coordination of work to ensure compliance with master schedule, system verification, testing, and submission of a final commissioning report.

Additional Information:

LocationWashington, DC
Construction Value $250,000
OwnerGeneral Services Administration