UMBC, Tech Center Chiller Replacement

Over the course of the contract, Henry Adams managed the entire design team and provided studies, analysis and design for renovations and retrofits of University property. Properties included a variety of campuses around Baltimore managed by UMB, including University of Maryland Baltimore, Towson University and University of Maryland Baltimore County.

 In this specific task order, Henry Adams provided project management and mechanical and electrical engineering design for this project to replace two 215-ton centrifugal chillers with two 325-ton units. The project also included adding variable speed drives to the existing secondary chilled water pumps, adding variable speed drives to the existing motors on the cooling towers and adding a purge ventilation system to comply with ASHRAE 15 in the event of a refrigerant leak.

Additional Information:

Completion Date
Construction Value $800,000
OwnerUniversity of Maryland, Baltimore County
ArchitectHord Coplan Macht